Friday, May 25, 2012

Bricks Done, roof next

Our brickies finished yesterday and there were guys on our roof getting it ready.

Gutters are to go up on Tuesday and well have half a roof by the end of the week

Sunday, May 20, 2012

Bricks are almost finished!

We're really happy with how our bricks are looking (and theyll look even better once they're clean!)

The brickies are almost done now

Tuesday, May 8, 2012

Plumbing and Frame Finished

On our visit today we've found our frame finished (they hadnt done our pitched entry) and some sliding doors installed for our ensuite and WIR.

The plumbing has also been done and our bath tub installed

Thursday, May 3, 2012

Brickies

We had a phone call from our SS about our brick window sill under the servery window.

So we went straight up to the block and had a look around (first time I've been there after the slab was poured)